Killtest provides accurate 74-343 Certification Preparation Material for your best result in Microsoft Certification Exam. Killtest is sworn to provide you follow in the Microsoft 74-343 test. All that you possess to do is to go through our creation, and you present take to straits an inquiring you pauperization to screw whatever Microsoft 74-343 practice questions, Messages on MS Project Exam 74-343 Questions 74-343 Practice Exam, which testament exploit you, locomote your certifications. This sort of aid is provided by Microsoft 74-343 practice questions Killtest, this site is fully accoutered with 91 real exam questions and answers, which will ply you, yielding your certifications. We give you a bright career opportunity by providing 74-343 Managing Projects with Microsoft Project 2013. Killtest Messages on MS Project Exam 74-343 Questions 74-343 Practice Exam will introduce you to the core logic of various subjects so that you not only learn, but you also understand various technologies and subjects. Killtest Messages on MS Project Exam 74-343 Questions 74-343 Practice Exam help individuals increase their understanding of exam objectives and become familiar with the testing format.

Microsoft Project 74-343 Practice Exam | Killtest Microsoft 74-343 Test Questions | 2017 New 74-343 Study Materials

You are a project manager who uses Project Professional 2013.You work on a software development project, and the Project Management Office (PMO) requires you to enter project costs associated with all work completed on your project.You receive invoices for $5,000 for software licenses and $150 for supplies.Software licensing costs are associated with Task A: Obtain Software License.Supply costs are associated with Task H: Project Management Administration.You need to enter the costs into your project schedule.Which two steps should you perform? (Each correct answer presents part of the solution.Choose two.)
A.Create a material resource for Supplies and Software License.
B.Assign the Supply cost resource to Task H, assign the Software License cost resource to Task A, and enter the actual costs using the Task Usage - Cost table for both Task H and A.
C.Assign the Supply material resource to Task H, assign the Software License material resource to Task A, and enter the actual costs using the Task Usage - Cost table for both Task H and A.
D.Create a cost resource for Supplies and Software License.
Answer: DB

You are a project manager who uses Project Professional 2013.After updating a project schedule, you want to determine the amount of time that the schedule has slipped from the original scheduled dates.
You need a graphical view that shows the current schedule to baseline.Which view should you use?
A.Tracking Gantt view
B.Leveling Gantt view
C.Detail Gantt view
D.Gantt Chart view
Answer: A

You are a project manager, and your organization uses Project Professional 2013.You have created a detailed project schedule and have identified two tasks that are causing your resource to be overallocated.You need to use the Team Planner to reassign these tasks from the overallocated resources to underallocated resources with the same skill set.What should you do?
A.Right-click the resource and reassign it to the underallocated resource.
B.Drag the underallocated resource on the task to reassign it.
C.Right-click the task and reassign it to the underallocated resource.
D.Drag one of the tasks from the overallocated resource to the Unassigned Tasks section.
Answer: C

You are a project manager, and your organization uses Project Professional 2013.You have created a detailed project schedule and have identified two tasks that are causing your resource to be overallocated.You need to use the Team Planner to reassign these tasks from the overallocated resources to underallocated resources with the same skill set.What should you do?
A.Right-click the resource and reassign it to the underallocated resource.
B.Drag the underallocated resource on the task to reassign it.
C.Right-click the task and reassign it to the underallocated resource.
D.Drag one of the tasks from the overallocated resource to the Unassigned Tasks section.
Answer: C

You are a project manager who uses Project Professional 2013.Your organization migrates all project plans from Microsoft Excel to Project Professional 2013.One of the directors of the company has several years of experience using Excel Pivot Tables to analyze and make decisions about projects.You need to enable project managers to view relevant project information in Excel Pivot Tables.What should you do?
A.Create a report by using the Visual Reports feature.Select Microsoft Excel and choose relevant data to view in the report.
B.Download and install the Microsoft Project to Pivot Table Tool and generate a new Excel Pivot Table by selecting the current project.
C.Use the Excel Data From Other Sources feature to access your project file.
D.Create a Report view by using the new Built-In Dashboards and Reports feature and export to Excel.
Answer: A

IT Certifications offered by Microsoft have international value and acceptance. Like other world-known certifications, Microsoft has also an extensive range of its IT certifications. People all over the world like to opt for Microsoft certification to make their careers more strengthened and successful. Messages on MS Project Exam 74-343 Questions 74-343 Practice Exam can easily be addressed if you select a good training institute for your guidance relating to the Microsoft Certification 74-343 test. The Microsoft 74-343 test questions are a very good way of testing the real potentials of the 74-343 Managing Projects with Microsoft Project 2013 candidates and with time the means of accessing their capabilities are improving. It is important for you to prepare yourself for the 74-343 exam keeping in view all the modern trends only then you will be able succeed in the 74-343 exam with Killtest Messages on MS Project Exam 74-343 Questions 74-343 Practice Exam.

Killtest has released Messages on MS Project Exam 74-343 Questions 74-343 Practice Exam for the success. Take Killtest Microsoft Project 74-343 practice exam for example, you can just buy it online. To some candidates who are short of Microsoft 74-343 exam, Killtest is a good way for Microsoft 74-343 success. The latest or most helpful messages on the Messages on MS Project Exam 74-343 Questions 74-343 Practice Exam will be posted at Killtest. Getting the technical certifications of IT has become the major objective of countless candidates. IT sector has achieved fabulous prestige on the entire planet due to its role in the progress of present world. Their target is to become one of the best IT experts globally. In Killtest Messages on MS Project Exam 74-343 Questions 74-343 Practice Exam, you can find 74-343 real questions and answers. With answers you get from the question is unique. The reason behind the prestige of 74-343 exam questions and answers is that they're designed to make individuals comfortable in their preparation in accordance with the structure of the Messages on MS Project Exam 74-343 Questions 74-343 Practice Exam.
Comments Feed Comments Feed: http://www.ns0-101.com/feed.asp?q=comment&id=3060
UTF-8 Encoding Trackback URL: http://www.ns0-101.com/trackback.asp?id=3060

There is no comment on this article.

Post Comment
Smilies
[smile] [confused] [cool] [cry]
[eek] [angry] [wink] [sweat]
[lol] [stun] [razz] [redface]
[rolleyes] [sad] [yes] [no]
[heart] [star] [music] [idea]
Enable UBB Codes
Auto Convert URL
Show Smilies
Hidden Comment
Username:   Password:   Register Now?
Security Code * Please Enter the Security Code